Both sides of Thepkrasattri Rd (Route 402) are to be affected from in front of Wat Tha Reua, located south of the Heroines Monument, all the way to the Thai Watsadu outlet near Thalang Town, PEA Thalang explained in a notice issued late yesterday (Apr 22).
The work began yesterday and will continue through to June 30, PEA Thalang noted.
The work is required to allow the Phuket Highways office to proceed with the construction of the underpass to be built at the Heroines Monument, the notice explained.
“In this regard, the Provincial Electricity Authority Thalang branch apologises for the inconvenience,” the notice read.
Areas adjacent to where the power lines are being moved are expected to experience power outages while the work is carried out.
Today (Apr 23), the low-voltage power system at Redwood House in Noo 2, Srisoonthorn, was affected from 9am to 4:30pm.
Tomorrow (Apr 24), the high-voltage power network supplying the Supalai Essence and Supalai Hill housing estates ‒ both located west of the Heroines Monument in Moo 3, Srisoonthorn ‒ will be affected from 9am to 4:30pm.
People living or working in any areas near where the work is being carried out along Thepkrasattri Rd are advised to check the PEA Thalang official Facebook page daily for any late announcements of power outages.